title: "Switchgear lead times"
description: "Gilbane’s Q1 2026 survey reported 49–82 weeks for medium-voltage switchgear after order or fabrication release."
image: "https://industrialleadtimes.com/og.jpg"
url: "https://industrialleadtimes.com/indexes/switchgear/"
last_updated: "2026-11-28"
---

> Site index for agents: https://industrialleadtimes.com/llms.txt

# Switchgear lead times

Gilbane’s Q1 2026 survey reported [49–82 weeks](https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21) for medium-voltage switchgear after order or fabrication release. [Read the evidence](https://industrialleadtimes.com/gilbane-mv-switchgear-q1-2026/).

## Published readings by period

Use the reading type and clock to match evidence to your purchase.

1.  ### 2026-Fall
    
    *   [Medium- and low-voltage switchgear](https://industrialleadtimes.com/skanska-switchgear-fall-2026/) · Market report · [52+ weeks](https://interactive.usa.skanska.com/fall-2026-construction-market-trends/supply-chain)
2.  ### 2026-Q1
    
    *   [Low-voltage switchgear](https://industrialleadtimes.com/gilbane-lv-switchgear-q1-2026/) · Market report · [32–54 weeks](https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21)
    *   [Medium-voltage switchgear](https://industrialleadtimes.com/gilbane-mv-switchgear-q1-2026/) · Market report · [49–82 weeks](https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21)
3.  ### 2022-Summer
    
    *   [Medium-voltage switchgear](https://industrialleadtimes.com/skanska-mv-switchgear-summer-2022/) · Market report · [18–24 weeks](https://interactive.usa.skanska.com/skanska-construction-trends-summer-2022-1/p/7)

## Switchgear buying questions

### What date starts the Gilbane estimate?

The estimate begins when the order or fabrication is released. Put engineering and submittal approval on separate lines in the schedule.

### How are open-ended readings shown?

A plus sign marks a lower bound. The upper end stays blank in the data export.

### Which specifications help line up switchgear quotes?

Match voltage, ampacity, short-circuit rating, lineup size, relay package, enclosure and acceptance test scope.

## Request quotes

Send the part specification, quantity, delivery ZIP code and deadline to the procurement desk.

Request received by the procurement desk.

If the form fails, email [desk@industrialleadtimes.com](mailto:desk@industrialleadtimes.com) with your brief.

## Browse the indexes

*   [Castings](https://industrialleadtimes.com/indexes/castings/)
*   [Forgings](https://industrialleadtimes.com/indexes/forgings/)
*   [Motors](https://industrialleadtimes.com/indexes/motors/)
*   [MV cable](https://industrialleadtimes.com/indexes/mv-cable/)
*   [Valves](https://industrialleadtimes.com/indexes/valves/)
*   [Precast](https://industrialleadtimes.com/indexes/precast/)
*   [Switchgear](https://industrialleadtimes.com/indexes/switchgear/)
*   [HVAC equipment](https://industrialleadtimes.com/indexes/hvac/)

```json
{"@context":"https://schema.org","@graph":[{"@type":"FAQPage","mainEntity":[{"@type":"Question","name":"What date starts the Gilbane estimate?","acceptedAnswer":{"@type":"Answer","text":"The estimate begins when the order or fabrication is released. Put engineering and submittal approval on separate lines in the schedule."}},{"@type":"Question","name":"How are open-ended readings shown?","acceptedAnswer":{"@type":"Answer","text":"A plus sign marks a lower bound. The upper end stays blank in the data export."}},{"@type":"Question","name":"Which specifications help line up switchgear quotes?","acceptedAnswer":{"@type":"Answer","text":"Match voltage, ampacity, short-circuit rating, lineup size, relay package, enclosure and acceptance test scope."}}]},{"@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"Tracker","item":"https://industrialleadtimes.com/"},{"@type":"ListItem","position":2,"name":"Indexes","item":"https://industrialleadtimes.com/indexes/"},{"@type":"ListItem","position":3,"name":"Switchgear","item":"https://industrialleadtimes.com/indexes/switchgear/"}]}]}
```