# Industrial Lead Times: Industrial lead times Rochester Public Utilities recorded 22–36 weeks across its January 2026 bids for four 15 kV cable specifications. Albertville’s domestic 36-inch butterfly valve quote was 30–38 weeks in its May 2026 filing. Compare dated bids, reported deliveries and factory estimates across industrial categories, with a source excerpt for every reading. Source: https://industrialleadtimes.com/ ## Fields - Reading period: Date or reporting period given by the publisher. - Category: Product category used by the tracker. - Scope: Product and configuration covered by the reading. - Publisher: Organization that disclosed the lead time. - Reading type: Kind of evidence behind the lead time. - Lead-time basis: The interval or milestone covered by the reading. - Lead time as stated: Source duration with original units preserved. - Weeks from: Lower end in weeks. Exact readings have equal lower and upper values. - Weeks to: Upper end in weeks. Open-ended readings have an empty upper value. - Source excerpt: Verbatim excerpt with layout whitespace normalized. - Source location: Page, section, bid item or column to inspect. - Quoted table value: Exact lead-time cell where the excerpt is a separate table heading or item label. - Technical family: Independent technical reference matched on product family. - Technical excerpt: Verbatim evidence from the technical reference. - Lead-time band: Planning band computed from the lower bound in weeks. - Range width: Upper minus lower bound in weeks. - Duration format: Classifies the published bounds as a single duration, bounded range or lower bound only. ## 16-inch metal-seated ball valve via TIPS contract URL: https://industrialleadtimes.com/georgetown-16-inch-ball-commitment/ Website: https://d2kbkoa27fdvtw.cloudfront.net/georgetown/3262b069f83b761f31ecd02a8e1c63250.pdf Verified: 2026-11-28 32–36 weeks for 16-inch metal-seated ball valve via TIPS contract. City of Georgetown, Texas reports this as delivery commitment evidence. - Tags: Valves - Reading period: 2023-10-12 - Category: Valves - Scope: 16-inch metal-seated ball valve via TIPS contract - Publisher: City of Georgetown, Texas - Reading type: Delivery commitment - Lead-time basis: Contract delivery - Lead time as stated: 32–36 weeks - Weeks from: 32 - Weeks to: 36 - Source excerpt: the manufacturer has committed to delivering the valve in 32-36 weeks. - Source location: Parkside–Round Rock interconnect - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 26 to under 52 weeks - Range width: 4 - Duration format: Bounded range Sources: 1. City of Georgetown, Texas · Parkside–Round Rock interconnect https://d2kbkoa27fdvtw.cloudfront.net/georgetown/3262b069f83b761f31ecd02a8e1c63250.pdf (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## 5 hp IE3 premium-efficiency motor URL: https://industrialleadtimes.com/calnext-5hp-ie3/ Website: https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 Verified: 2026-11-28 2 weeks for 5 hp IE3 premium-efficiency motor. CalNEXT reports this as supplier benchmark evidence. - Tags: Motors - Reading period: 2025-01-02 - Category: Motors - Scope: 5 hp IE3 premium-efficiency motor - Publisher: CalNEXT - Reading type: Supplier benchmark - Lead-time basis: Equipment lead time - Lead time as stated: 2 weeks - Weeks from: 2 - Weeks to: 2 - Source excerpt: IE3 motor with a lead time of roughly two weeks. - Source location: Final report, p. 13 - Quoted table value: not published - Technical family: Industrial electric motor systems - Technical excerpt: United States Industrial Electric Motor Systems Market Opportunities Assessment - Lead-time band: Under 4 weeks - Range width: 0 - Duration format: Single duration Sources: 1. CalNEXT · Final report, p. 13 https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 (accessed 2026-11-28) 2. DOE industrial motor systems resources https://www.energy.gov/cmei/ito/motor-systems (accessed 2026-11-28) ## 665 mm forged steel disc for Flender URL: https://industrialleadtimes.com/flender-perforated-disc-actual/ Website: https://siderforgerossi.com/fast-track-flender-project/ Verified: 2026-11-28 4 weeks for 665 mm forged steel disc for Flender. Siderforgerossi Group reports this as reported delivery evidence. - Tags: Forgings - Reading period: 2026-09-14 - Category: Forgings - Scope: 665 mm forged steel disc for Flender - Publisher: Siderforgerossi Group - Reading type: Reported delivery - Lead-time basis: Fast-track delivery - Lead time as stated: 4 weeks - Weeks from: 4 - Weeks to: 4 - Source excerpt: was delivered in 4 weeks, achieving a 50% reduction in standard delivery time - Source location: Flender case study - Quoted table value: not published - Technical family: Forged metal components - Technical excerpt: Forging entails shaping metal using compressive forces from a press. - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Siderforgerossi Group · Flender case study https://siderforgerossi.com/fast-track-flender-project/ (accessed 2026-11-28) 2. BCG overview of the forging process https://web-assets.bcg.com/pdf-src/prod-live/fixing-aerospaces-supply-chain-for-casting-and-forging.pdf (accessed 2026-11-28) ## 665 mm forged steel disc for Flender, standard URL: https://industrialleadtimes.com/flender-perforated-disc-standard/ Website: https://siderforgerossi.com/fast-track-flender-project/ Verified: 2026-11-28 8 weeks for 665 mm forged steel disc for Flender, standard. Siderforgerossi Group reports this as supplier benchmark evidence. - Tags: Forgings - Reading period: 2026-09-14 - Category: Forgings - Scope: 665 mm forged steel disc for Flender, standard - Publisher: Siderforgerossi Group - Reading type: Supplier benchmark - Lead-time basis: Standard delivery - Lead time as stated: 8 weeks - Weeks from: 8 - Weeks to: 8 - Source excerpt: 4 weeks instead of 8: a 50% reduction in standard delivery time - Source location: Flender case study - Quoted table value: not published - Technical family: Forged metal components - Technical excerpt: Forging entails shaping metal using compressive forces from a press. - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Siderforgerossi Group · Flender case study https://siderforgerossi.com/fast-track-flender-project/ (accessed 2026-11-28) 2. BCG overview of the forging process https://web-assets.bcg.com/pdf-src/prod-live/fixing-aerospaces-supply-chain-for-casting-and-forging.pdf (accessed 2026-11-28) ## Air-cooled chillers URL: https://industrialleadtimes.com/gilbane-air-chillers/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 14–23 weeks for Air-cooled chillers. Gilbane Building Company reports this as market report evidence. - Tags: HVAC equipment - Reading period: 2026-Q1 - Category: HVAC equipment - Scope: Air-cooled chillers - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 14–23 weeks - Weeks from: 14 - Weeks to: 23 - Source excerpt: Chillers (Air Cooled) 14-23 weeks - Source location: Q1 2026 lead-time table - Quoted table value: not published - Technical family: Chilled-water plant equipment - Technical excerpt: Air-cooled chillers use fans to blow air over the condenser, while water-cooled chillers transfer heat to a water loop - Lead-time band: 12 to under 26 weeks - Range width: 9 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Trane chiller technical guide https://www.trane.com/commercial/north-america/us/en/about-us/newsroom/glossary/chillers.html (accessed 2026-11-28) ## Alternate domestic 36-inch butterfly valve, first quote URL: https://industrialleadtimes.com/albertville-domestic-alternate-a/ Website: https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 Verified: 2026-11-28 46 weeks for Alternate domestic 36-inch butterfly valve, first quote. Municipal Utilities Board of Albertville reports this as public bid evidence. - Tags: Valves - Reading period: 2026-05-04 - Category: Valves - Scope: Alternate domestic 36-inch butterfly valve, first quote - Publisher: Municipal Utilities Board of Albertville - Reading type: Public bid - Lead-time basis: Quoted lead time - Lead time as stated: 46 weeks - Weeks from: 46 - Weeks to: 46 - Source excerpt: The lead times quoted by these manufacturers were 46 Weeks, 30-36 Weeks, and 30-36 Weeks, respectively. - Source location: Waiver request, first alternate domestic quote - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 26 to under 52 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Municipal Utilities Board of Albertville · Waiver request, first alternate domestic quote https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Alternate domestic 36-inch butterfly valve, second quote URL: https://industrialleadtimes.com/albertville-domestic-alternate-b/ Website: https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 Verified: 2026-11-28 30–36 weeks for Alternate domestic 36-inch butterfly valve, second quote. Municipal Utilities Board of Albertville reports this as public bid evidence. - Tags: Valves - Reading period: 2026-05-04 - Category: Valves - Scope: Alternate domestic 36-inch butterfly valve, second quote - Publisher: Municipal Utilities Board of Albertville - Reading type: Public bid - Lead-time basis: Quoted lead time - Lead time as stated: 30–36 weeks - Weeks from: 30 - Weeks to: 36 - Source excerpt: The lead times quoted by these manufacturers were 46 Weeks, 30-36 Weeks, and 30-36 Weeks, respectively. - Source location: Waiver request, second alternate domestic quote - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 26 to under 52 weeks - Range width: 6 - Duration format: Bounded range Sources: 1. Municipal Utilities Board of Albertville · Waiver request, second alternate domestic quote https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Alternate domestic 36-inch butterfly valve, third quote URL: https://industrialleadtimes.com/albertville-domestic-alternate-c/ Website: https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 Verified: 2026-11-28 30–36 weeks for Alternate domestic 36-inch butterfly valve, third quote. Municipal Utilities Board of Albertville reports this as public bid evidence. - Tags: Valves - Reading period: 2026-05-04 - Category: Valves - Scope: Alternate domestic 36-inch butterfly valve, third quote - Publisher: Municipal Utilities Board of Albertville - Reading type: Public bid - Lead-time basis: Quoted lead time - Lead time as stated: 30–36 weeks - Weeks from: 30 - Weeks to: 36 - Source excerpt: The lead times quoted by these manufacturers were 46 Weeks, 30-36 Weeks, and 30-36 Weeks, respectively. - Source location: Waiver request, third alternate domestic quote - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 26 to under 52 weeks - Range width: 6 - Duration format: Bounded range Sources: 1. Municipal Utilities Board of Albertville · Waiver request, third alternate domestic quote https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Atomac AKH2 PFA 2-inch ductile-iron ball valve URL: https://industrialleadtimes.com/flowserve-atomac-akh2-2-inch/ Website: https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf Verified: 2026-11-28 4 weeks for Atomac AKH2 PFA 2-inch ductile-iron ball valve. Flowserve reports this as factory estimate evidence. - Tags: Valves - Reading period: 2024-01-22 - Category: Valves - Scope: Atomac AKH2 PFA 2-inch ductile-iron ball valve - Publisher: Flowserve - Reading type: Factory estimate - Lead-time basis: Manufacturing lead time - Lead time as stated: 4 weeks - Weeks from: 4 - Weeks to: 4 - Source excerpt: Atomac AKH2 PFA - Size 2" - Ductile Iron 4 - Source location: CVO table, Atomac lined ball valves - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Flowserve · CVO table, Atomac lined ball valves https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Atomac AKH2 PFA 4-inch ductile-iron ball valve URL: https://industrialleadtimes.com/flowserve-atomac-akh2-4-inch/ Website: https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf Verified: 2026-11-28 12 weeks for Atomac AKH2 PFA 4-inch ductile-iron ball valve. Flowserve reports this as factory estimate evidence. - Tags: Valves - Reading period: 2024-01-22 - Category: Valves - Scope: Atomac AKH2 PFA 4-inch ductile-iron ball valve - Publisher: Flowserve - Reading type: Factory estimate - Lead-time basis: Manufacturing lead time - Lead time as stated: 12 weeks - Weeks from: 12 - Weeks to: 12 - Source excerpt: Atomac AKH2 PFA - Size 4" - Ductile Iron 12 - Source location: CVO table, Atomac lined ball valves - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Flowserve · CVO table, Atomac lined ball valves https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Atomac AKH2A PFA 4-inch ductile-iron ball valve URL: https://industrialleadtimes.com/flowserve-atomac-akh2a-4-inch/ Website: https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf Verified: 2026-11-28 18 weeks for Atomac AKH2A PFA 4-inch ductile-iron ball valve. Flowserve reports this as factory estimate evidence. - Tags: Valves - Reading period: 2024-01-22 - Category: Valves - Scope: Atomac AKH2A PFA 4-inch ductile-iron ball valve - Publisher: Flowserve - Reading type: Factory estimate - Lead-time basis: Manufacturing lead time - Lead time as stated: 18 weeks - Weeks from: 18 - Weeks to: 18 - Source excerpt: Atomac AKH2A PFA - Size 4" - Ductile Iron 18 - Source location: CVO table, Atomac lined ball valves - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Flowserve · CVO table, Atomac lined ball valves https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Bonfiglioli motor with nonstandard flange URL: https://industrialleadtimes.com/acorn-bonfiglioli-flange-replacement/ Website: https://www.acorn-ind.co.uk/insight/fast-response-to-motor-failure-saves-production/ Verified: 2026-11-28 8 weeks for Bonfiglioli motor with nonstandard flange. ACORN Industrial Services reports this as supplier estimate evidence. - Tags: Motors - Reading period: 2025-07-22 - Category: Motors - Scope: Bonfiglioli motor with nonstandard flange - Publisher: ACORN Industrial Services - Reading type: Supplier estimate - Lead-time basis: OEM replacement - Lead time as stated: 8 weeks - Weeks from: 8 - Weeks to: 8 - Source excerpt: The specialist motor had an 8-week OEM lead time - Source location: Case study, Quick facts - Quoted table value: not published - Technical family: Industrial electric motor systems - Technical excerpt: United States Industrial Electric Motor Systems Market Opportunities Assessment - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. ACORN Industrial Services · Case study, Quick facts https://www.acorn-ind.co.uk/insight/fast-response-to-motor-failure-saves-production/ (accessed 2026-11-28) 2. DOE industrial motor systems resources https://www.energy.gov/cmei/ito/motor-systems (accessed 2026-11-28) ## Border States / Prysmian — 15 kV 1/0 solid aluminum cable in duct URL: https://industrialleadtimes.com/rochester-2246-border-states/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 30–32 weeks for Border States / Prysmian — 15 kV 1/0 solid aluminum cable in duct. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: Border States / Prysmian — 15 kV 1/0 solid aluminum cable in duct - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 30–32 weeks - Weeks from: 30 - Weeks to: 32 - Source excerpt: Wire in Duct, AL, 15kV, 1/0 Solid, 1/C - Source location: RPU item 1 · stock 2246 · requested 27,000 ft · Border States / Prysmian - Quoted table value: 30-32 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 1 · stock 2246 · requested 27,000 ft · Border States / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Border States / Prysmian — 15 kV 1/0 solid jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-2247-border-states/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 24–26 weeks for Border States / Prysmian — 15 kV 1/0 solid jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: Border States / Prysmian — 15 kV 1/0 solid jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 24–26 weeks - Weeks from: 24 - Weeks to: 26 - Source excerpt: Wire, AL, 15kV, 1/0 Solid, 1/C, Jacketed - Source location: RPU item 2 · stock 2247 · requested 99,900 ft · Border States / Prysmian - Quoted table value: 24-26 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 2 · stock 2247 · requested 99,900 ft · Border States / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Border States / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-11042-border-states/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 24–26 weeks for Border States / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: Border States / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 24–26 weeks - Weeks from: 24 - Weeks to: 26 - Source excerpt: Wire, AL, 15 kV, 4/0 Stranded, 1/C, Jacketed 220m - Source location: RPU item 3 · stock 11042 · requested 10,000 ft · Border States / Prysmian - Quoted table value: 24-26 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 3 · stock 11042 · requested 10,000 ft · Border States / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Border States / Prysmian — 15 kV 750 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-16294-border-states/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 24–26 weeks for Border States / Prysmian — 15 kV 750 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: Border States / Prysmian — 15 kV 750 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 24–26 weeks - Weeks from: 24 - Weeks to: 26 - Source excerpt: Wire, AL, 15 kV, 750 Stranded, 1/C Jacketed 220m - Source location: RPU item 4 · stock 16294 · requested 66,000 ft · Border States / Prysmian - Quoted table value: 24-26 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 4 · stock 16294 · requested 66,000 ft · Border States / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Cold Springs Road concrete box culvert URL: https://industrialleadtimes.com/west-point-cold-springs-box-culvert/ Website: https://www.utah.gov/pmn/files/1333141.pdf#page=48 Verified: 2026-11-28 8 weeks for Cold Springs Road concrete box culvert. City of West Point, Utah reports this as buyer estimate evidence. - Tags: Precast - Reading period: 2025-10-07 - Category: Precast - Scope: Cold Springs Road concrete box culvert - Publisher: City of West Point, Utah - Reading type: Buyer estimate - Lead-time basis: Purchase lead time - Lead time as stated: 8 weeks - Weeks from: 8 - Weeks to: 8 - Source excerpt: It recently came to our attention that the lead time to purchase the box culvert is about eight weeks - Source location: City Council staff report, p. 48 - Quoted table value: not published - Technical family: Precast concrete drainage structures - Technical excerpt: Precast concrete box and 3-sided culverts are incredibly versatile - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. City of West Point, Utah · City Council staff report, p. 48 https://www.utah.gov/pmn/files/1333141.pdf#page=48 (accessed 2026-11-28) 2. NPCA technical overview of box culverts https://precast.org/products/box-3-sided-culverts/ (accessed 2026-11-28) ## Commercial-grade air handling units URL: https://industrialleadtimes.com/gilbane-commercial-ahu/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 16–20 weeks for Commercial-grade air handling units. Gilbane Building Company reports this as market report evidence. - Tags: HVAC equipment - Reading period: 2026-Q1 - Category: HVAC equipment - Scope: Commercial-grade air handling units - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 16–20 weeks - Weeks from: 16 - Weeks to: 20 - Source excerpt: AHUs (Commercial Grade) 16-20 weeks - Source location: Q1 2026 lead-time table - Quoted table value: not published - Technical family: Air distribution and rooftop HVAC - Technical excerpt: A typical VAV system consists of a rooftop unit, water-cooled self-contained unit, or an air handling unit - Lead-time band: 12 to under 26 weeks - Range width: 4 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Trane VAV system guide https://www.trane.com/commercial/north-america/us/en/products-systems/systems/intelligent-variable-air-systems.html (accessed 2026-11-28) ## Commonly stocked 1–20 hp motors URL: https://industrialleadtimes.com/calnext-stocked-motors/ Website: https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 Verified: 2026-11-28 1–2 weeks for Commonly stocked 1–20 hp motors. CalNEXT reports this as pilot benchmark evidence. - Tags: Motors - Reading period: 2025-01-02 - Category: Motors - Scope: Commonly stocked 1–20 hp motors - Publisher: CalNEXT - Reading type: Pilot benchmark - Lead-time basis: Equipment lead time - Lead time as stated: 1–2 weeks - Weeks from: 1 - Weeks to: 2 - Source excerpt: manufacturer are roughly 1 to 2 weeks. - Source location: Final report, p. 13 - Quoted table value: not published - Technical family: Industrial electric motor systems - Technical excerpt: United States Industrial Electric Motor Systems Market Opportunities Assessment - Lead-time band: Under 4 weeks - Range width: 1 - Duration format: Bounded range Sources: 1. CalNEXT · Final report, p. 13 https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 (accessed 2026-11-28) 2. DOE industrial motor systems resources https://www.energy.gov/cmei/ito/motor-systems (accessed 2026-11-28) ## Custom air handling units URL: https://industrialleadtimes.com/gilbane-custom-ahu/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 20–33 weeks for Custom air handling units. Gilbane Building Company reports this as market report evidence. - Tags: HVAC equipment - Reading period: 2026-Q1 - Category: HVAC equipment - Scope: Custom air handling units - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 20–33 weeks - Weeks from: 20 - Weeks to: 33 - Source excerpt: AHUs (Custom) 20-33 weeks Stable - Source location: Q1 2026 lead-time table - Quoted table value: not published - Technical family: Air distribution and rooftop HVAC - Technical excerpt: A typical VAV system consists of a rooftop unit, water-cooled self-contained unit, or an air handling unit - Lead-time band: 12 to under 26 weeks - Range width: 13 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Trane VAV system guide https://www.trane.com/commercial/north-america/us/en/products-systems/systems/intelligent-variable-air-systems.html (accessed 2026-11-28) ## Custom-order advanced motor URL: https://industrialleadtimes.com/calnext-custom-motor/ Website: https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 Verified: 2026-11-28 6 weeks for Custom-order advanced motor. CalNEXT reports this as reported wait evidence. - Tags: Motors - Reading period: 2025-01-02 - Category: Motors - Scope: Custom-order advanced motor - Publisher: CalNEXT - Reading type: Reported wait - Lead-time basis: Equipment lead time - Lead time as stated: 6 weeks - Weeks from: 6 - Weeks to: 6 - Source excerpt: a six-week lead time because they needed a custom-order - Source location: Final report, p. 13 - Quoted table value: not published - Technical family: Industrial electric motor systems - Technical excerpt: United States Industrial Electric Motor Systems Market Opportunities Assessment - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. CalNEXT · Final report, p. 13 https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 (accessed 2026-11-28) 2. DOE industrial motor systems resources https://www.energy.gov/cmei/ito/motor-systems (accessed 2026-11-28) ## Domestic 36-inch ductile-iron butterfly valve URL: https://industrialleadtimes.com/albertville-domestic-butterfly/ Website: https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 Verified: 2026-11-28 30–38 weeks for Domestic 36-inch ductile-iron butterfly valve. Municipal Utilities Board of Albertville reports this as public bid evidence. - Tags: Valves - Reading period: 2026-05-04 - Category: Valves - Scope: Domestic 36-inch ductile-iron butterfly valve - Publisher: Municipal Utilities Board of Albertville - Reading type: Public bid - Lead-time basis: Quoted lead time - Lead time as stated: 30–38 weeks - Weeks from: 30 - Weeks to: 38 - Source excerpt: 36-Inch Butterfly Valve Misc. Waiver Information - Source location: Waiver request, domestic column, lead-time table - Quoted table value: 30-38 - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 26 to under 52 weeks - Range width: 8 - Duration format: Bounded range Sources: 1. Municipal Utilities Board of Albertville · Waiver request, domestic column, lead-time table https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Durco BTV 2–12-inch TFE-lined butterfly valves URL: https://industrialleadtimes.com/flowserve-durco-btv-tfe/ Website: https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf Verified: 2026-11-28 18 weeks for Durco BTV 2–12-inch TFE-lined butterfly valves. Flowserve reports this as factory estimate evidence. - Tags: Valves - Reading period: 2024-01-22 - Category: Valves - Scope: Durco BTV 2–12-inch TFE-lined butterfly valves - Publisher: Flowserve - Reading type: Factory estimate - Lead-time basis: Manufacturing lead time - Lead time as stated: 18 weeks - Weeks from: 18 - Weeks to: 18 - Source excerpt: Wafer & Lug, Std. TFE Liner, PFA Disc (480 / 481 Model) 18 - Source location: CVO table, Durco plug and butterfly valves - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Flowserve · CVO table, Durco plug and butterfly valves https://preprodflowserve.bigmachines.com/bmfsweb/preprodflowserve/image/CVO_Downloads/FLS_CVO_leadtime_charts.pdf (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Foundry backlogs in 2021–2022 URL: https://industrialleadtimes.com/state-line-casting-backlogs-2021-22/ Website: https://www.slfcastings.com/switching-foundries-backlogs/ Verified: 2026-11-28 20+ weeks for Foundry backlogs in 2021–2022. State Line Foundries reports this as backlog evidence. - Tags: Castings - Reading period: 2021–2022 - Category: Castings - Scope: Foundry backlogs in 2021–2022 - Publisher: State Line Foundries - Reading type: Backlog - Lead-time basis: Backlog of work - Lead time as stated: 20+ weeks - Weeks from: 20 - Weeks to: not published - Source excerpt: In 2021 and 2022, casting backlogs were out 20-plus weeks for most foundries - Source location: September 27, 2023 interview - Quoted table value: not published - Technical family: Near-net-shape metal forming - Technical excerpt: Technical and Business Challenges for Infrastructure-Scale Near Net Shape Components - Lead-time band: 12 to under 26 weeks - Range width: not published - Duration format: Lower bound only Sources: 1. State Line Foundries · September 27, 2023 interview https://www.slfcastings.com/switching-foundries-backlogs/ (accessed 2026-11-28) 2. DOE workshop on industrial-scale forming https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf (accessed 2026-11-28) ## IE4 motors from surveyed manufacturer URL: https://industrialleadtimes.com/calnext-ie4/ Website: https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 Verified: 2026-11-28 2–4 weeks for IE4 motors from surveyed manufacturer. CalNEXT reports this as supplier benchmark evidence. - Tags: Motors - Reading period: 2025-01-02 - Category: Motors - Scope: IE4 motors from surveyed manufacturer - Publisher: CalNEXT - Reading type: Supplier benchmark - Lead-time basis: Equipment lead time - Lead time as stated: 2–4 weeks - Weeks from: 2 - Weeks to: 4 - Source excerpt: is two to four weeks, depending on - Source location: Final report, p. 13 - Quoted table value: not published - Technical family: Industrial electric motor systems - Technical excerpt: United States Industrial Electric Motor Systems Market Opportunities Assessment - Lead-time band: Under 4 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. CalNEXT · Final report, p. 13 https://calnext.com/wp-content/uploads/2025/01/ET23SWE0068_Advanced-Motors-Channel-Partner-Support-and-Measure-Package-Development_Final-Report.pdf#page=19 (accessed 2026-11-28) 2. DOE industrial motor systems resources https://www.energy.gov/cmei/ito/motor-systems (accessed 2026-11-28) ## Imported 36-inch ductile-iron butterfly valve URL: https://industrialleadtimes.com/albertville-imported-butterfly/ Website: https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 Verified: 2026-11-28 6–8 weeks for Imported 36-inch ductile-iron butterfly valve. Municipal Utilities Board of Albertville reports this as public bid evidence. - Tags: Valves - Reading period: 2026-05-04 - Category: Valves - Scope: Imported 36-inch ductile-iron butterfly valve - Publisher: Municipal Utilities Board of Albertville - Reading type: Public bid - Lead-time basis: Quoted lead time - Lead time as stated: 6–8 weeks - Weeks from: 6 - Weeks to: 8 - Source excerpt: 36-Inch Butterfly Valve Misc. Waiver Information - Source location: Waiver request, foreign column, lead-time table - Quoted table value: 6-8 - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 4 to under 12 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Municipal Utilities Board of Albertville · Waiver request, foreign column, lead-time table https://www.epa.gov/system/files/documents/2026-06/municipal-utilities-board-albertville-al-butterfly-valve-waiver-request.pdf#page=2 (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## IRBY / Okonite — 15 kV 1/0 solid aluminum cable in duct URL: https://industrialleadtimes.com/rochester-2246-irby/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 32–34 weeks for IRBY / Okonite — 15 kV 1/0 solid aluminum cable in duct. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: IRBY / Okonite — 15 kV 1/0 solid aluminum cable in duct - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 32–34 weeks - Weeks from: 32 - Weeks to: 34 - Source excerpt: Wire in Duct, AL, 15kV, 1/0 Solid, 1/C - Source location: RPU item 1 · stock 2246 · requested 27,000 ft · IRBY / Okonite - Quoted table value: 32-34 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 1 · stock 2246 · requested 27,000 ft · IRBY / Okonite https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## IRBY / Okonite — 15 kV 1/0 solid jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-2247-irby/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 30–32 weeks for IRBY / Okonite — 15 kV 1/0 solid jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: IRBY / Okonite — 15 kV 1/0 solid jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 30–32 weeks - Weeks from: 30 - Weeks to: 32 - Source excerpt: Wire, AL, 15kV, 1/0 Solid, 1/C, Jacketed - Source location: RPU item 2 · stock 2247 · requested 99,900 ft · IRBY / Okonite - Quoted table value: 30-32 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 2 · stock 2247 · requested 99,900 ft · IRBY / Okonite https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## IRBY / Okonite — 15 kV 4/0 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-11042-irby/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 34–36 weeks for IRBY / Okonite — 15 kV 4/0 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: IRBY / Okonite — 15 kV 4/0 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 34–36 weeks - Weeks from: 34 - Weeks to: 36 - Source excerpt: Wire, AL, 15 kV, 4/0 Stranded, 1/C, Jacketed 220m - Source location: RPU item 3 · stock 11042 · requested 10,000 ft · IRBY / Okonite - Quoted table value: 34-36 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 3 · stock 11042 · requested 10,000 ft · IRBY / Okonite https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## IRBY / Okonite — 15 kV 750 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-16294-irby/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 26–28 weeks for IRBY / Okonite — 15 kV 750 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: IRBY / Okonite — 15 kV 750 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 26–28 weeks - Weeks from: 26 - Weeks to: 28 - Source excerpt: Wire, AL, 15 kV, 750 Stranded, 1/C Jacketed 220m - Source location: RPU item 4 · stock 16294 · requested 66,000 ft · IRBY / Okonite - Quoted table value: 26-28 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 4 · stock 16294 · requested 66,000 ft · IRBY / Okonite https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Large nuclear forgings URL: https://industrialleadtimes.com/doe-large-nuclear-forgings/ Website: https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf#page=36 Verified: 2026-11-28 24–48 months for Large nuclear forgings. US Department of Energy reports this as workshop estimate evidence. - Tags: Forgings - Reading period: 2024-02 - Category: Forgings - Scope: Large nuclear forgings - Publisher: US Department of Energy - Reading type: Workshop estimate - Lead-time basis: Acquisition - Lead time as stated: 24–48 months - Weeks from: 104.4 - Weeks to: 208.7 - Source excerpt: 24–48 months for large forgings used for nuclear applications - Source location: Workshop breakout group, PDF page 36 - Quoted table value: not published - Technical family: Forged metal components - Technical excerpt: Forging entails shaping metal using compressive forces from a press. - Lead-time band: 52 weeks and up - Range width: 104.3 - Duration format: Bounded range Sources: 1. US Department of Energy · Workshop breakout group, PDF page 36 https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf#page=36 (accessed 2026-11-28) 2. BCG overview of the forging process https://web-assets.bcg.com/pdf-src/prod-live/fixing-aerospaces-supply-chain-for-casting-and-forging.pdf (accessed 2026-11-28) ## Low-voltage switchgear URL: https://industrialleadtimes.com/gilbane-lv-switchgear-q1-2026/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 32–54 weeks for Low-voltage switchgear. Gilbane Building Company reports this as market report evidence. - Tags: Switchgear - Reading period: 2026-Q1 - Category: Switchgear - Scope: Low-voltage switchgear - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 32–54 weeks - Weeks from: 32 - Weeks to: 54 - Source excerpt: 32-54 weeks (slight improvement in deliveries) - Source location: Q1 2026 lead-time table, Switchgear LV - Quoted table value: not published - Technical family: Electrical distribution switching and protection - Technical excerpt: provides centralized control and protection of medium-voltage power equipment - Lead-time band: 26 to under 52 weeks - Range width: 22 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table, Switchgear LV https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Eaton distribution switchgear overview https://www.eaton.com/us/en-us/products/medium-voltage-power-distribution-control-systems/switchgear.html (accessed 2026-11-28) ## Main water injection valve, expedited delivery URL: https://industrialleadtimes.com/severn-replacement-valve-delivery/ Website: https://www.severnvalve.com/severn-exceeds-expectations/ Verified: 2026-11-28 20 weeks for Main water injection valve, expedited delivery. Severn reports this as reported delivery evidence. - Tags: Valves - Reading period: 2022-11-22 - Category: Valves - Scope: Main water injection valve, expedited delivery - Publisher: Severn - Reading type: Reported delivery - Lead-time basis: Replacement delivery - Lead time as stated: 20 weeks - Weeks from: 20 - Weeks to: 20 - Source excerpt: the new valve in 20 weeks. - Source location: Replacement case study - Quoted table value: not published - Technical family: Process flow valves and service parts - Technical excerpt: An isolation valve stops the flow of gas, liquid, slurry or powder. - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Severn · Replacement case study https://www.severnvalve.com/severn-exceeds-expectations/ (accessed 2026-11-28) 2. Emerson process valve overview https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Main water injection valve, standard replacement URL: https://industrialleadtimes.com/severn-replacement-valve-standard/ Website: https://www.severnvalve.com/severn-exceeds-expectations/ Verified: 2026-11-28 30 weeks for Main water injection valve, standard replacement. Severn reports this as supplier benchmark evidence. - Tags: Valves - Reading period: 2022-11-22 - Category: Valves - Scope: Main water injection valve, standard replacement - Publisher: Severn - Reading type: Supplier benchmark - Lead-time basis: Replacement delivery - Lead time as stated: 30 weeks - Weeks from: 30 - Weeks to: 30 - Source excerpt: a complete valve replacement is around 30 weeks - Source location: Replacement case study - Quoted table value: not published - Technical family: Process flow valves and service parts - Technical excerpt: An isolation valve stops the flow of gas, liquid, slurry or powder. - Lead-time band: 26 to under 52 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Severn · Replacement case study https://www.severnvalve.com/severn-exceeds-expectations/ (accessed 2026-11-28) 2. Emerson process valve overview https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## McCann Concrete Products 8 × 6 ft box culvert sections URL: https://industrialleadtimes.com/lebanon-mccann-box-culvert/ Website: https://www.lebanonmissouri.org/DocumentCenter/View/36123/Council-Bill-No-6290--Purchase-Precast-Culvert-for-Kansas-McCann-Concrete-Products#page=3 Verified: 2026-11-28 94 days for McCann Concrete Products 8 × 6 ft box culvert sections. City of Lebanon, Missouri reports this as public bid evidence. - Tags: Precast - Reading period: 2022-05-17 - Category: Precast - Scope: McCann Concrete Products 8 × 6 ft box culvert sections - Publisher: City of Lebanon, Missouri - Reading type: Public bid - Lead-time basis: From executed contract - Lead time as stated: 94 days - Weeks from: 13.4 - Weeks to: 13.4 - Source excerpt: 94 days after receipt of executed - Source location: ITB ST-08-220517-F-652, Exhibit A - Quoted table value: not published - Technical family: Precast concrete drainage structures - Technical excerpt: Precast concrete box and 3-sided culverts are incredibly versatile - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. City of Lebanon, Missouri · ITB ST-08-220517-F-652, Exhibit A https://www.lebanonmissouri.org/DocumentCenter/View/36123/Council-Bill-No-6290--Purchase-Precast-Culvert-for-Kansas-McCann-Concrete-Products#page=3 (accessed 2026-11-28) 2. NPCA technical overview of box culverts https://precast.org/products/box-3-sided-culverts/ (accessed 2026-11-28) ## Medium- and low-voltage switchgear URL: https://industrialleadtimes.com/skanska-switchgear-fall-2026/ Website: https://interactive.usa.skanska.com/fall-2026-construction-market-trends/supply-chain Verified: 2026-11-28 52+ weeks for Medium- and low-voltage switchgear. Skanska USA Building reports this as market report evidence. - Tags: Switchgear - Reading period: 2026-Fall - Category: Switchgear - Scope: Medium- and low-voltage switchgear - Publisher: Skanska USA Building - Reading type: Market report - Lead-time basis: Excludes submittals - Lead time as stated: 52+ weeks - Weeks from: 52 - Weeks to: not published - Source excerpt: lead times for electrical gear increased over the past quarter, specifically for medium- and low-voltage switchgear, which now exceed 52 weeks. - Source location: Fall 2026, Electrical - Quoted table value: not published - Technical family: Electrical distribution switching and protection - Technical excerpt: provides centralized control and protection of medium-voltage power equipment - Lead-time band: 52 weeks and up - Range width: not published - Duration format: Lower bound only Sources: 1. Skanska USA Building · Fall 2026, Electrical https://interactive.usa.skanska.com/fall-2026-construction-market-trends/supply-chain (accessed 2026-11-28) 2. Eaton distribution switchgear overview https://www.eaton.com/us/en-us/products/medium-voltage-power-distribution-control-systems/switchgear.html (accessed 2026-11-28) ## Medium-voltage cable URL: https://industrialleadtimes.com/skanska-mv-cable-spring-2023/ Website: https://view.ceros.com/skanska/skanska-construction-trends-spring-23/p/7 Verified: 2026-11-28 30–45 weeks for Medium-voltage cable. Skanska USA Building reports this as market report evidence. - Tags: MV cable - Reading period: 2023-Spring - Category: MV cable - Scope: Medium-voltage cable - Publisher: Skanska USA Building - Reading type: Market report - Lead-time basis: Market lead time - Lead time as stated: 30–45 weeks - Weeks from: 30 - Weeks to: 45 - Source excerpt: However, medium voltage cable lead times are still in the 30-45 week range. - Source location: Spring 2023, Electrical - Quoted table value: not published - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 15 - Duration format: Bounded range Sources: 1. Skanska USA Building · Spring 2023, Electrical https://view.ceros.com/skanska/skanska-construction-trends-spring-23/p/7 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Medium-voltage switchgear URL: https://industrialleadtimes.com/skanska-mv-switchgear-summer-2022/ Website: https://interactive.usa.skanska.com/skanska-construction-trends-summer-2022-1/p/7 Verified: 2026-11-28 18–24 weeks for Medium-voltage switchgear. Skanska USA Building reports this as market report evidence. - Tags: Switchgear - Reading period: 2022-Summer - Category: Switchgear - Scope: Medium-voltage switchgear - Publisher: Skanska USA Building - Reading type: Market report - Lead-time basis: Market lead time - Lead time as stated: 18–24 weeks - Weeks from: 18 - Weeks to: 24 - Source excerpt: medium voltage switchgear lead times are between 18 and 24 weeks. - Source location: Summer 2022, Electrical - Quoted table value: not published - Technical family: Electrical distribution switching and protection - Technical excerpt: provides centralized control and protection of medium-voltage power equipment - Lead-time band: 12 to under 26 weeks - Range width: 6 - Duration format: Bounded range Sources: 1. Skanska USA Building · Summer 2022, Electrical https://interactive.usa.skanska.com/skanska-construction-trends-summer-2022-1/p/7 (accessed 2026-11-28) 2. Eaton distribution switchgear overview https://www.eaton.com/us/en-us/products/medium-voltage-power-distribution-control-systems/switchgear.html (accessed 2026-11-28) ## Medium-voltage switchgear URL: https://industrialleadtimes.com/gilbane-mv-switchgear-q1-2026/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 49–82 weeks for Medium-voltage switchgear. Gilbane Building Company reports this as market report evidence. - Tags: Switchgear - Reading period: 2026-Q1 - Category: Switchgear - Scope: Medium-voltage switchgear - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 49–82 weeks - Weeks from: 49 - Weeks to: 82 - Source excerpt: 49-82 weeks (slight improvement in deliveries) - Source location: Q1 2026 lead-time table, Switchgear MV - Quoted table value: not published - Technical family: Electrical distribution switching and protection - Technical excerpt: provides centralized control and protection of medium-voltage power equipment - Lead-time band: 26 to under 52 weeks - Range width: 33 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table, Switchgear MV https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Eaton distribution switchgear overview https://www.eaton.com/us/en-us/products/medium-voltage-power-distribution-control-systems/switchgear.html (accessed 2026-11-28) ## Municipal Valve 16-inch metal-seated ball valve URL: https://industrialleadtimes.com/georgetown-municipal-16-inch-ball/ Website: https://d2kbkoa27fdvtw.cloudfront.net/georgetown/3262b069f83b761f31ecd02a8e1c63250.pdf Verified: 2026-11-28 40–44 weeks for Municipal Valve 16-inch metal-seated ball valve. City of Georgetown, Texas reports this as public bid evidence. - Tags: Valves - Reading period: 2023-10-12 - Category: Valves - Scope: Municipal Valve 16-inch metal-seated ball valve - Publisher: City of Georgetown, Texas - Reading type: Public bid - Lead-time basis: Standard quote - Lead time as stated: 40–44 weeks - Weeks from: 40 - Weeks to: 44 - Source excerpt: Municipal Valve stated the lead time for this valve is 40-44 weeks long. - Source location: Parkside–Round Rock interconnect - Quoted table value: not published - Technical family: Ball and butterfly isolation valves - Technical excerpt: including ball valves, butterfly valves, gate valves, globe valves - Lead-time band: 26 to under 52 weeks - Range width: 4 - Duration format: Bounded range Sources: 1. City of Georgetown, Texas · Parkside–Round Rock interconnect https://d2kbkoa27fdvtw.cloudfront.net/georgetown/3262b069f83b761f31ecd02a8e1c63250.pdf (accessed 2026-11-28) 2. Emerson isolation valve catalog https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## New forging orders in the US industry survey URL: https://industrialleadtimes.com/commerce-new-forging-orders-1992/ Website: https://www.bis.gov/media/documents/u.s.-forging-industry-may-8.pdf#page=9 Verified: 2026-11-28 39.3 weeks for New forging orders in the US industry survey. US Department of Commerce reports this as historical survey average evidence. - Tags: Forgings - Reading period: 1992-12 - Category: Forgings - Scope: New forging orders in the US industry survey - Publisher: US Department of Commerce - Reading type: Historical survey average - Lead-time basis: Reported procurement lead time - Lead time as stated: 39.3 weeks - Weeks from: 39.3 - Weeks to: 39.3 - Source excerpt: Forging lead times for new orders averaged 39.3 weeks, and for repeat business, 15.4 weeks. - Source location: Executive summary, printed page v - Quoted table value: not published - Technical family: Forged metal components - Technical excerpt: Forging entails shaping metal using compressive forces from a press. - Lead-time band: 26 to under 52 weeks - Range width: 0 - Duration format: Single duration Sources: 1. US Department of Commerce · Executive summary, printed page v https://www.bis.gov/media/documents/u.s.-forging-industry-may-8.pdf#page=9 (accessed 2026-11-28) 2. BCG overview of the forging process https://web-assets.bcg.com/pdf-src/prod-live/fixing-aerospaces-supply-chain-for-casting-and-forging.pdf (accessed 2026-11-28) ## Nonstandard imperial-shaft gearmotor URL: https://industrialleadtimes.com/acorn-imperial-shaft-gearmotor/ Website: https://www.acorn-ind.co.uk/insight/how-a-24-hour-gearmotor-repair-prevented-677-million-in-downtime/ Verified: 2026-11-28 4+ weeks for Nonstandard imperial-shaft gearmotor. ACORN Industrial Services reports this as supplier estimate evidence. - Tags: Motors - Reading period: 2026-07-13 - Category: Motors - Scope: Nonstandard imperial-shaft gearmotor - Publisher: ACORN Industrial Services - Reading type: Supplier estimate - Lead-time basis: Replacement arrival - Lead time as stated: 4+ weeks - Weeks from: 4 - Weeks to: not published - Source excerpt: a replacement from the original manufacturer would take a minimum of four weeks to arrive. - Source location: Case study, The Challenge - Quoted table value: not published - Technical family: Industrial electric motor systems - Technical excerpt: United States Industrial Electric Motor Systems Market Opportunities Assessment - Lead-time band: 4 to under 12 weeks - Range width: not published - Duration format: Lower bound only Sources: 1. ACORN Industrial Services · Case study, The Challenge https://www.acorn-ind.co.uk/insight/how-a-24-hour-gearmotor-repair-prevented-677-million-in-downtime/ (accessed 2026-11-28) 2. DOE industrial motor systems resources https://www.energy.gov/cmei/ito/motor-systems (accessed 2026-11-28) ## Nonstock 5–15 kV cable URL: https://industrialleadtimes.com/skanska-5-to-15kv-summer-2022/ Website: https://interactive.usa.skanska.com/skanska-construction-trends-summer-2022-1/p/7 Verified: 2026-11-28 14–20 weeks for Nonstock 5–15 kV cable. Skanska USA Building reports this as market report evidence. - Tags: MV cable - Reading period: 2022-Summer - Category: MV cable - Scope: Nonstock 5–15 kV cable - Publisher: Skanska USA Building - Reading type: Market report - Lead-time basis: Market lead time - Lead time as stated: 14–20 weeks - Weeks from: 14 - Weeks to: 20 - Source excerpt: now running 14 to 20 weeks if they’re not in stock - Source location: Summer 2022, Electrical - Quoted table value: not published - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 6 - Duration format: Bounded range Sources: 1. Skanska USA Building · Summer 2022, Electrical https://interactive.usa.skanska.com/skanska-construction-trends-summer-2022-1/p/7 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Power Line / Okonite 500 MCM Cu URD MV cable, 15 kV URL: https://industrialleadtimes.com/portland-okonite-500-mcm/ Website: https://www.portland-michigan.org/DocumentCenter/View/5356/20250804-Packet?bidId=#page=44 Verified: 2026-11-28 8–10 weeks for Power Line / Okonite 500 MCM Cu URD MV cable, 15 kV. City of Portland, Michigan reports this as public bid evidence. - Tags: MV cable - Reading period: 2025-08-04 - Category: MV cable - Scope: Power Line / Okonite 500 MCM Cu URD MV cable, 15 kV - Publisher: City of Portland, Michigan - Reading type: Public bid - Lead-time basis: Quoted lead time - Lead time as stated: 8–10 weeks - Weeks from: 8 - Weeks to: 10 - Source excerpt: Competitive bids were solicited for both products, with the following results: - Source location: Substation memo, Okonite row - Quoted table value: 8-10 weeks - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 4 to under 12 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. City of Portland, Michigan · Substation memo, Okonite row https://www.portland-michigan.org/DocumentCenter/View/5356/20250804-Packet?bidId=#page=44 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Price, Utah, 16 × 4 ft box culvert URL: https://industrialleadtimes.com/geneva-carbon-ave-box-culvert/ Website: https://www.utah.gov/pmn/files/1341541.pdf#page=2 Verified: 2026-11-28 6–7 weeks for Price, Utah, 16 × 4 ft box culvert. Geneva Pipe Company reports this as public bid evidence. - Tags: Precast - Reading period: 2025-10-23 - Category: Precast - Scope: Price, Utah, 16 × 4 ft box culvert - Publisher: Geneva Pipe Company - Reading type: Public bid - Lead-time basis: From submittal approval - Lead time as stated: 6–7 weeks - Weeks from: 6 - Weeks to: 7 - Source excerpt: LEAD TIME IS APPROX 6-7 WEEKS AFTER SUBMITTAL APPROVAL - Source location: Quote 56708, Carbon Ave canal crossing - Quoted table value: not published - Technical family: Precast concrete drainage structures - Technical excerpt: Precast concrete box and 3-sided culverts are incredibly versatile - Lead-time band: 4 to under 12 weeks - Range width: 1 - Duration format: Bounded range Sources: 1. Geneva Pipe Company · Quote 56708, Carbon Ave canal crossing https://www.utah.gov/pmn/files/1341541.pdf#page=2 (accessed 2026-11-28) 2. NPCA technical overview of box culverts https://precast.org/products/box-3-sided-culverts/ (accessed 2026-11-28) ## Repeat forging orders in the US industry survey URL: https://industrialleadtimes.com/commerce-repeat-forging-orders-1992/ Website: https://www.bis.gov/media/documents/u.s.-forging-industry-may-8.pdf#page=9 Verified: 2026-11-28 15.4 weeks for Repeat forging orders in the US industry survey. US Department of Commerce reports this as historical survey average evidence. - Tags: Forgings - Reading period: 1992-12 - Category: Forgings - Scope: Repeat forging orders in the US industry survey - Publisher: US Department of Commerce - Reading type: Historical survey average - Lead-time basis: Reported procurement lead time - Lead time as stated: 15.4 weeks - Weeks from: 15.4 - Weeks to: 15.4 - Source excerpt: Forging lead times for new orders averaged 39.3 weeks, and for repeat business, 15.4 weeks. - Source location: Executive summary, printed page v - Quoted table value: not published - Technical family: Forged metal components - Technical excerpt: Forging entails shaping metal using compressive forces from a press. - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. US Department of Commerce · Executive summary, printed page v https://www.bis.gov/media/documents/u.s.-forging-industry-may-8.pdf#page=9 (accessed 2026-11-28) 2. BCG overview of the forging process https://web-assets.bcg.com/pdf-src/prod-live/fixing-aerospaces-supply-chain-for-casting-and-forging.pdf (accessed 2026-11-28) ## RESCO / Kerite 500 MCM Cu URD MV cable, 15 kV URL: https://industrialleadtimes.com/portland-kerite-500-mcm/ Website: https://www.portland-michigan.org/DocumentCenter/View/5356/20250804-Packet?bidId=#page=44 Verified: 2026-11-28 10 weeks for RESCO / Kerite 500 MCM Cu URD MV cable, 15 kV. City of Portland, Michigan reports this as public bid evidence. - Tags: MV cable - Reading period: 2025-08-04 - Category: MV cable - Scope: RESCO / Kerite 500 MCM Cu URD MV cable, 15 kV - Publisher: City of Portland, Michigan - Reading type: Public bid - Lead-time basis: Quoted lead time - Lead time as stated: 10 weeks - Weeks from: 10 - Weeks to: 10 - Source excerpt: Competitive bids were solicited for both products, with the following results: - Source location: Substation memo, Kerite row - Quoted table value: 10 weeks - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. City of Portland, Michigan · Substation memo, Kerite row https://www.portland-michigan.org/DocumentCenter/View/5356/20250804-Packet?bidId=#page=44 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## RESCO / Prysmian — 15 kV 1/0 solid aluminum cable in duct URL: https://industrialleadtimes.com/rochester-2246-resco/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 31–33 weeks for RESCO / Prysmian — 15 kV 1/0 solid aluminum cable in duct. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: RESCO / Prysmian — 15 kV 1/0 solid aluminum cable in duct - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 31–33 weeks - Weeks from: 31 - Weeks to: 33 - Source excerpt: Wire in Duct, AL, 15kV, 1/0 Solid, 1/C - Source location: RPU item 1 · stock 2246 · requested 27,000 ft · RESCO / Prysmian - Quoted table value: 31-33 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 1 · stock 2246 · requested 27,000 ft · RESCO / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## RESCO / Prysmian — 15 kV 1/0 solid jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-2247-resco/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 25–27 weeks for RESCO / Prysmian — 15 kV 1/0 solid jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: RESCO / Prysmian — 15 kV 1/0 solid jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 25–27 weeks - Weeks from: 25 - Weeks to: 27 - Source excerpt: Wire, AL, 15kV, 1/0 Solid, 1/C, Jacketed - Source location: RPU item 2 · stock 2247 · requested 99,900 ft · RESCO / Prysmian - Quoted table value: 25-27 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 2 · stock 2247 · requested 99,900 ft · RESCO / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## RESCO / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-11042-resco/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 25–27 weeks for RESCO / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: RESCO / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 25–27 weeks - Weeks from: 25 - Weeks to: 27 - Source excerpt: Wire, AL, 15 kV, 4/0 Stranded, 1/C, Jacketed 220m - Source location: RPU item 3 · stock 11042 · requested 10,000 ft · RESCO / Prysmian - Quoted table value: 25-27 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 3 · stock 11042 · requested 10,000 ft · RESCO / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## RESCO / Prysmian — 15 kV 750 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-16294-resco/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 25–27 weeks for RESCO / Prysmian — 15 kV 750 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: RESCO / Prysmian — 15 kV 750 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 25–27 weeks - Weeks from: 25 - Weeks to: 27 - Source excerpt: Wire, AL, 15 kV, 750 Stranded, 1/C Jacketed 220m - Source location: RPU item 4 · stock 16294 · requested 66,000 ft · RESCO / Prysmian - Quoted table value: 25-27 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 4 · stock 16294 · requested 66,000 ft · RESCO / Prysmian https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Reverse-engineered high-strength steel castings URL: https://industrialleadtimes.com/cti-high-strength-steel-castings/ Website: https://www.foundrymag.com/molds-cores/article/21928864/metalcaster-adopts-3dp-keeps-its-focus-on-casting Verified: 2026-11-28 3 weeks for Reverse-engineered high-strength steel castings. Foundry Management & Technology reports this as reported production evidence. - Tags: Castings - Reading period: 2016-08-12 - Category: Castings - Scope: Reverse-engineered high-strength steel castings - Publisher: Foundry Management & Technology - Reading type: Reported production - Lead-time basis: Reverse engineering through manufacture - Lead time as stated: 3 weeks - Weeks from: 3 - Weeks to: 3 - Source excerpt: In just three weeks, Casting Technologies International managed to reverse engineer a component - Source location: Casting Technologies International case - Quoted table value: not published - Technical family: Near-net-shape metal forming - Technical excerpt: Technical and Business Challenges for Infrastructure-Scale Near Net Shape Components - Lead-time band: Under 4 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Foundry Management & Technology · Casting Technologies International case https://www.foundrymag.com/molds-cores/article/21928864/metalcaster-adopts-3dp-keeps-its-focus-on-casting (accessed 2026-11-28) 2. DOE workshop on industrial-scale forming https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf (accessed 2026-11-28) ## Rooftop HVAC units above 50 tons URL: https://industrialleadtimes.com/gilbane-rooftop-over-50/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 13–22 weeks for Rooftop HVAC units above 50 tons. Gilbane Building Company reports this as market report evidence. - Tags: HVAC equipment - Reading period: 2026-Q1 - Category: HVAC equipment - Scope: Rooftop HVAC units above 50 tons - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 13–22 weeks - Weeks from: 13 - Weeks to: 22 - Source excerpt: RTUs (>50 ton) 13-22 weeks - Source location: Q1 2026 lead-time table - Quoted table value: not published - Technical family: Air distribution and rooftop HVAC - Technical excerpt: A typical VAV system consists of a rooftop unit, water-cooled self-contained unit, or an air handling unit - Lead-time band: 12 to under 26 weeks - Range width: 9 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Trane VAV system guide https://www.trane.com/commercial/north-america/us/en/products-systems/systems/intelligent-variable-air-systems.html (accessed 2026-11-28) ## Rooftop HVAC units below 50 tons URL: https://industrialleadtimes.com/gilbane-rooftop-under-50/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 12–18 weeks for Rooftop HVAC units below 50 tons. Gilbane Building Company reports this as market report evidence. - Tags: HVAC equipment - Reading period: 2026-Q1 - Category: HVAC equipment - Scope: Rooftop HVAC units below 50 tons - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 12–18 weeks - Weeks from: 12 - Weeks to: 18 - Source excerpt: RTUs (<50 ton) 12-18 weeks - Source location: Q1 2026 lead-time table - Quoted table value: not published - Technical family: Air distribution and rooftop HVAC - Technical excerpt: A typical VAV system consists of a rooftop unit, water-cooled self-contained unit, or an air handling unit - Lead-time band: 12 to under 26 weeks - Range width: 6 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Trane VAV system guide https://www.trane.com/commercial/north-america/us/en/products-systems/systems/intelligent-variable-air-systems.html (accessed 2026-11-28) ## Scurlock Industries box culvert bid, 291 linear ft URL: https://industrialleadtimes.com/lebanon-scurlock-box-culvert/ Website: https://www.lebanonmissouri.org/DocumentCenter/View/36123/Council-Bill-No-6290--Purchase-Precast-Culvert-for-Kansas-McCann-Concrete-Products#page=3 Verified: 2026-11-28 14–20 weeks for Scurlock Industries box culvert bid, 291 linear ft. City of Lebanon, Missouri reports this as public bid evidence. - Tags: Precast - Reading period: 2022-05-17 - Category: Precast - Scope: Scurlock Industries box culvert bid, 291 linear ft - Publisher: City of Lebanon, Missouri - Reading type: Public bid - Lead-time basis: From award - Lead time as stated: 14–20 weeks - Weeks from: 14 - Weeks to: 20 - Source excerpt: Approx. 14-20 weeks after award - Source location: ITB ST-08-220517-F-652, Exhibit A - Quoted table value: not published - Technical family: Precast concrete drainage structures - Technical excerpt: Precast concrete box and 3-sided culverts are incredibly versatile - Lead-time band: 12 to under 26 weeks - Range width: 6 - Duration format: Bounded range Sources: 1. City of Lebanon, Missouri · ITB ST-08-220517-F-652, Exhibit A https://www.lebanonmissouri.org/DocumentCenter/View/36123/Council-Bill-No-6290--Purchase-Precast-Culvert-for-Kansas-McCann-Concrete-Products#page=3 (accessed 2026-11-28) 2. NPCA technical overview of box culverts https://precast.org/products/box-3-sided-culverts/ (accessed 2026-11-28) ## Steel casting best-practice example URL: https://industrialleadtimes.com/steel-best-practice-roadmap/ Website: https://www.energy.gov/sites/prod/files/2013/11/f4/roadmap.pdf#page=31 Verified: 2026-11-28 4 weeks for Steel casting best-practice example. Cast Metal Coalition reports this as industry benchmark evidence. - Tags: Castings - Reading period: 1998-01 - Category: Castings - Scope: Steel casting best-practice example - Publisher: Cast Metal Coalition - Reading type: Industry benchmark - Lead-time basis: Procurement - Lead time as stated: 4 weeks - Weeks from: 4 - Weeks to: 4 - Source excerpt: "best practice" can bring this time down to about 4 weeks in some cases. - Source location: Lead time - Quoted table value: not published - Technical family: Near-net-shape metal forming - Technical excerpt: Technical and Business Challenges for Infrastructure-Scale Near Net Shape Components - Lead-time band: 4 to under 12 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Cast Metal Coalition · Lead time https://www.energy.gov/sites/prod/files/2013/11/f4/roadmap.pdf#page=31 (accessed 2026-11-28) 2. DOE workshop on industrial-scale forming https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf (accessed 2026-11-28) ## Steel casting plant backlog after sharp demand declines URL: https://industrialleadtimes.com/sfsa-steel-plant-downturn-backlog/ Website: https://www.sfsa.org/sfsa-casteel-reporter-march-2026/ Verified: 2026-11-28 6–8 weeks for Steel casting plant backlog after sharp demand declines. Steel Founders’ Society of America reports this as backlog evidence. - Tags: Castings - Reading period: 2026-03-23 - Category: Castings - Scope: Steel casting plant backlog after sharp demand declines - Publisher: Steel Founders’ Society of America - Reading type: Backlog - Lead-time basis: Backlog of work - Lead time as stated: 6–8 weeks - Weeks from: 6 - Weeks to: 8 - Source excerpt: Sharp declines in demand reduce the reported backlog to 6 to 8 weeks. - Source location: Figure 2 commentary - Quoted table value: not published - Technical family: Near-net-shape metal forming - Technical excerpt: Technical and Business Challenges for Infrastructure-Scale Near Net Shape Components - Lead-time band: 4 to under 12 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Steel Founders’ Society of America · Figure 2 commentary https://www.sfsa.org/sfsa-casteel-reporter-march-2026/ (accessed 2026-11-28) 2. DOE workshop on industrial-scale forming https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf (accessed 2026-11-28) ## Steel casting plant backlog in normal conditions URL: https://industrialleadtimes.com/sfsa-steel-plant-normal-backlog/ Website: https://www.sfsa.org/sfsa-casteel-reporter-march-2026/ Verified: 2026-11-28 8–10 weeks for Steel casting plant backlog in normal conditions. Steel Founders’ Society of America reports this as backlog evidence. - Tags: Castings - Reading period: 2026-03-23 - Category: Castings - Scope: Steel casting plant backlog in normal conditions - Publisher: Steel Founders’ Society of America - Reading type: Backlog - Lead-time basis: Backlog of work - Lead time as stated: 8–10 weeks - Weeks from: 8 - Weeks to: 10 - Source excerpt: Backlog in normal business conditions is 8 to 10 weeks. - Source location: Figure 2 commentary - Quoted table value: not published - Technical family: Near-net-shape metal forming - Technical excerpt: Technical and Business Challenges for Infrastructure-Scale Near Net Shape Components - Lead-time band: 4 to under 12 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Steel Founders’ Society of America · Figure 2 commentary https://www.sfsa.org/sfsa-casteel-reporter-march-2026/ (accessed 2026-11-28) 2. DOE workshop on industrial-scale forming https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf (accessed 2026-11-28) ## Steel casting procurement URL: https://industrialleadtimes.com/steel-procurement-roadmap/ Website: https://www.energy.gov/sites/prod/files/2013/11/f4/roadmap.pdf#page=31 Verified: 2026-11-28 20–40 weeks for Steel casting procurement. Cast Metal Coalition reports this as industry benchmark evidence. - Tags: Castings - Reading period: 1998-01 - Category: Castings - Scope: Steel casting procurement - Publisher: Cast Metal Coalition - Reading type: Industry benchmark - Lead-time basis: Procurement - Lead time as stated: 20–40 weeks - Weeks from: 20 - Weeks to: 40 - Source excerpt: steel castings typically take 20 to 40 weeks to procure - Source location: Lead time - Quoted table value: not published - Technical family: Near-net-shape metal forming - Technical excerpt: Technical and Business Challenges for Infrastructure-Scale Near Net Shape Components - Lead-time band: 12 to under 26 weeks - Range width: 20 - Duration format: Bounded range Sources: 1. Cast Metal Coalition · Lead time https://www.energy.gov/sites/prod/files/2013/11/f4/roadmap.pdf#page=31 (accessed 2026-11-28) 2. DOE workshop on industrial-scale forming https://www.energy.gov/sites/default/files/2024-02/near-net-shape-workshop-report-2024.pdf (accessed 2026-11-28) ## Volume purchase of 5 kV cable URL: https://industrialleadtimes.com/skanska-5kv-spring-2022/ Website: https://interactive.usa.skanska.com/skanska-construction-trends-spring-2022/p/5 Verified: 2026-11-28 20–28 weeks for Volume purchase of 5 kV cable. Skanska USA Building reports this as market report evidence. - Tags: MV cable - Reading period: 2022-Spring - Category: MV cable - Scope: Volume purchase of 5 kV cable - Publisher: Skanska USA Building - Reading type: Market report - Lead-time basis: Market lead time - Lead time as stated: 20–28 weeks - Weeks from: 20 - Weeks to: 28 - Source excerpt: Lead times for highly specific items, such as 5kV medium voltage cable in volume, are running 20–28 weeks - Source location: Spring 2022, Electrical - Quoted table value: not published - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 8 - Duration format: Bounded range Sources: 1. Skanska USA Building · Spring 2022, Electrical https://interactive.usa.skanska.com/skanska-construction-trends-spring-2022/p/5 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## Water injection valve trim, expedited delivery URL: https://industrialleadtimes.com/severn-trim-delivery/ Website: https://www.severnvalve.com/severn-exceeds-expectations/ Verified: 2026-11-28 12 weeks for Water injection valve trim, expedited delivery. Severn reports this as reported delivery evidence. - Tags: Valves - Reading period: 2022-11-22 - Category: Valves - Scope: Water injection valve trim, expedited delivery - Publisher: Severn - Reading type: Reported delivery - Lead-time basis: Trim delivery - Lead time as stated: 12 weeks - Weeks from: 12 - Weeks to: 12 - Source excerpt: set of trims in 12 weeks - Source location: Replacement case study - Quoted table value: not published - Technical family: Process flow valves and service parts - Technical excerpt: An isolation valve stops the flow of gas, liquid, slurry or powder. - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Severn · Replacement case study https://www.severnvalve.com/severn-exceeds-expectations/ (accessed 2026-11-28) 2. Emerson process valve overview https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Water injection valve trim, standard lead URL: https://industrialleadtimes.com/severn-trim-standard/ Website: https://www.severnvalve.com/severn-exceeds-expectations/ Verified: 2026-11-28 22 weeks for Water injection valve trim, standard lead. Severn reports this as supplier benchmark evidence. - Tags: Valves - Reading period: 2022-11-22 - Category: Valves - Scope: Water injection valve trim, standard lead - Publisher: Severn - Reading type: Supplier benchmark - Lead-time basis: Trim availability - Lead time as stated: 22 weeks - Weeks from: 22 - Weeks to: 22 - Source excerpt: trim parts is 22 weeks - Source location: Replacement case study - Quoted table value: not published - Technical family: Process flow valves and service parts - Technical excerpt: An isolation valve stops the flow of gas, liquid, slurry or powder. - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Severn · Replacement case study https://www.severnvalve.com/severn-exceeds-expectations/ (accessed 2026-11-28) 2. Emerson process valve overview https://www.emerson.com/en/final-control/catalog/products-and-software/valves/isolation-valves (accessed 2026-11-28) ## Water-cooled chillers above 1,000 tons URL: https://industrialleadtimes.com/gilbane-water-chillers-over-1000/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 28–44 weeks for Water-cooled chillers above 1,000 tons. Gilbane Building Company reports this as market report evidence. - Tags: HVAC equipment - Reading period: 2026-Q1 - Category: HVAC equipment - Scope: Water-cooled chillers above 1,000 tons - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 28–44 weeks - Weeks from: 28 - Weeks to: 44 - Source excerpt: Chillers (Water Cooled, >1000 tons) 28-44 weeks - Source location: Q1 2026 lead-time table - Quoted table value: not published - Technical family: Chilled-water plant equipment - Technical excerpt: Air-cooled chillers use fans to blow air over the condenser, while water-cooled chillers transfer heat to a water loop - Lead-time band: 26 to under 52 weeks - Range width: 16 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Trane chiller technical guide https://www.trane.com/commercial/north-america/us/en/about-us/newsroom/glossary/chillers.html (accessed 2026-11-28) ## Water-cooled chillers below 1,000 tons URL: https://industrialleadtimes.com/gilbane-water-chillers-under-1000/ Website: https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 Verified: 2026-11-28 18–30 weeks for Water-cooled chillers below 1,000 tons. Gilbane Building Company reports this as market report evidence. - Tags: HVAC equipment - Reading period: 2026-Q1 - Category: HVAC equipment - Scope: Water-cooled chillers below 1,000 tons - Publisher: Gilbane Building Company - Reading type: Market report - Lead-time basis: From order or fabrication release - Lead time as stated: 18–30 weeks - Weeks from: 18 - Weeks to: 30 - Source excerpt: Chillers (Water Cooled, <1000 tons) 18-30 weeks - Source location: Q1 2026 lead-time table - Quoted table value: not published - Technical family: Chilled-water plant equipment - Technical excerpt: Air-cooled chillers use fans to blow air over the condenser, while water-cooled chillers transfer heat to a water loop - Lead-time band: 12 to under 26 weeks - Range width: 12 - Duration format: Bounded range Sources: 1. Gilbane Building Company · Q1 2026 lead-time table https://info.gilbaneco.com/hubfs/Q1%202026%20Market%20Conditions%20Report_Print.pdf#page=21 (accessed 2026-11-28) 2. Trane chiller technical guide https://www.trane.com/commercial/north-america/us/en/about-us/newsroom/glossary/chillers.html (accessed 2026-11-28) ## WESCO / CME — 15 kV 1/0 solid aluminum cable in duct URL: https://industrialleadtimes.com/rochester-2246-wesco-cme/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 32–34 weeks for WESCO / CME — 15 kV 1/0 solid aluminum cable in duct. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / CME — 15 kV 1/0 solid aluminum cable in duct - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 32–34 weeks - Weeks from: 32 - Weeks to: 34 - Source excerpt: Wire in Duct, AL, 15kV, 1/0 Solid, 1/C - Source location: RPU item 1 · stock 2246 · requested 27,000 ft · WESCO / CME - Quoted table value: 32-34 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 1 · stock 2246 · requested 27,000 ft · WESCO / CME https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO / CME — 15 kV 1/0 solid jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-2247-wesco-cme/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 30–32 weeks for WESCO / CME — 15 kV 1/0 solid jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / CME — 15 kV 1/0 solid jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 30–32 weeks - Weeks from: 30 - Weeks to: 32 - Source excerpt: Wire, AL, 15kV, 1/0 Solid, 1/C, Jacketed - Source location: RPU item 2 · stock 2247 · requested 99,900 ft · WESCO / CME - Quoted table value: 30-32 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 2 · stock 2247 · requested 99,900 ft · WESCO / CME https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO / CME — 15 kV 4/0 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-11042-wesco-cme/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 34–36 weeks for WESCO / CME — 15 kV 4/0 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / CME — 15 kV 4/0 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 34–36 weeks - Weeks from: 34 - Weeks to: 36 - Source excerpt: Wire, AL, 15 kV, 4/0 Stranded, 1/C, Jacketed 220m - Source location: RPU item 3 · stock 11042 · requested 10,000 ft · WESCO / CME - Quoted table value: 34-36 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 3 · stock 11042 · requested 10,000 ft · WESCO / CME https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO / CME — 15 kV 750 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-16294-wesco-cme/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 26–28 weeks for WESCO / CME — 15 kV 750 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / CME — 15 kV 750 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 26–28 weeks - Weeks from: 26 - Weeks to: 28 - Source excerpt: Wire, AL, 15 kV, 750 Stranded, 1/C Jacketed 220m - Source location: RPU item 4 · stock 16294 · requested 66,000 ft · WESCO / CME - Quoted table value: 26-28 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. Rochester Public Utilities · RPU item 4 · stock 16294 · requested 66,000 ft · WESCO / CME https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO / LS Cable — 15 kV 1/0 solid aluminum cable in duct URL: https://industrialleadtimes.com/rochester-2246-wesco-ls/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 26 weeks for WESCO / LS Cable — 15 kV 1/0 solid aluminum cable in duct. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / LS Cable — 15 kV 1/0 solid aluminum cable in duct - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 26 weeks - Weeks from: 26 - Weeks to: 26 - Source excerpt: Wire in Duct, AL, 15kV, 1/0 Solid, 1/C - Source location: RPU item 1 · stock 2246 · requested 27,000 ft · WESCO / LS Cable - Quoted table value: 26 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 26 to under 52 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Rochester Public Utilities · RPU item 1 · stock 2246 · requested 27,000 ft · WESCO / LS Cable https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO / LS Cable — 15 kV 1/0 solid jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-2247-wesco-ls/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 22 weeks for WESCO / LS Cable — 15 kV 1/0 solid jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / LS Cable — 15 kV 1/0 solid jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 22 weeks - Weeks from: 22 - Weeks to: 22 - Source excerpt: Wire, AL, 15kV, 1/0 Solid, 1/C, Jacketed - Source location: RPU item 2 · stock 2247 · requested 99,900 ft · WESCO / LS Cable - Quoted table value: 22 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Rochester Public Utilities · RPU item 2 · stock 2247 · requested 99,900 ft · WESCO / LS Cable https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO / LS Cable — 15 kV 4/0 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-11042-wesco-ls/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 22 weeks for WESCO / LS Cable — 15 kV 4/0 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / LS Cable — 15 kV 4/0 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 22 weeks - Weeks from: 22 - Weeks to: 22 - Source excerpt: Wire, AL, 15 kV, 4/0 Stranded, 1/C, Jacketed 220m - Source location: RPU item 3 · stock 11042 · requested 10,000 ft · WESCO / LS Cable - Quoted table value: 22 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Rochester Public Utilities · RPU item 3 · stock 11042 · requested 10,000 ft · WESCO / LS Cable https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO / LS Cable — 15 kV 750 stranded jacketed aluminum cable URL: https://industrialleadtimes.com/rochester-16294-wesco-ls/ Website: https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 Verified: 2026-11-28 22 weeks for WESCO / LS Cable — 15 kV 750 stranded jacketed aluminum cable. Rochester Public Utilities reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-01-30 - Category: MV cable - Scope: WESCO / LS Cable — 15 kV 750 stranded jacketed aluminum cable - Publisher: Rochester Public Utilities - Reading type: Public bid - Lead-time basis: Bid lead time - Lead time as stated: 22 weeks - Weeks from: 22 - Weeks to: 22 - Source excerpt: Wire, AL, 15 kV, 750 Stranded, 1/C Jacketed 220m - Source location: RPU item 4 · stock 16294 · requested 66,000 ft · WESCO / LS Cable - Quoted table value: 22 - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 12 to under 26 weeks - Range width: 0 - Duration format: Single duration Sources: 1. Rochester Public Utilities · RPU item 4 · stock 16294 · requested 66,000 ft · WESCO / LS Cable https://d3n9y02raazwpg.cloudfront.net/rochestermn/f9c40f30-c642-11f0-a7da-005056a89546-f50ddd73-1307-4d4b-8301-1402d356b22a-1770847045.pdf#page=18 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28) ## WESCO 1/0 15 kV primary cable, 24,000 ft URL: https://industrialleadtimes.com/concord-wesco-15kv/ Website: https://concordnc.gov/Portals/0/Concord/Departments/Clerk/Council%20Agenda/50485/02-12-2026%20Agenda11111.pdf?ver=8NPMY8EgVJcsOyNjxiVYsA%3D%3D#page=6 Verified: 2026-11-28 8–10 weeks for WESCO 1/0 15 kV primary cable, 24,000 ft. City of Concord, North Carolina reports this as public bid evidence. - Tags: MV cable - Reading period: 2026-02-12 - Category: MV cable - Scope: WESCO 1/0 15 kV primary cable, 24,000 ft - Publisher: City of Concord, North Carolina - Reading type: Public bid - Lead-time basis: Estimated delivery lead - Lead time as stated: 8–10 weeks - Weeks from: 8 - Weeks to: 10 - Source excerpt: The estimated lead time of 8 to 10 weeks is exceptionally good - Source location: Council agenda, electrical cable purchase - Quoted table value: not published - Technical family: Medium-voltage cable - Technical excerpt: Medium Voltage Cables 2.4kV and above - Lead-time band: 4 to under 12 weeks - Range width: 2 - Duration format: Bounded range Sources: 1. City of Concord, North Carolina · Council agenda, electrical cable purchase https://concordnc.gov/Portals/0/Concord/Departments/Clerk/Council%20Agenda/50485/02-12-2026%20Agenda11111.pdf?ver=8NPMY8EgVJcsOyNjxiVYsA%3D%3D#page=6 (accessed 2026-11-28) 2. Okonite cable class catalog https://www.okonite.com/product-catalog (accessed 2026-11-28)