Price, Utah, 16 × 4 ft box culvert

6–7 weeks

“LEAD TIME IS APPROX 6-7 WEEKS AFTER SUBMITTAL APPROVAL”
Geneva Pipe Company · Quote 56708, Carbon Ave canal crossing · Checked 28 Nov 2026

Reading details

Reading period
2025-10-23
Publisher
Geneva Pipe Company
Reading type
Public bid
Lead-time basis
From submittal approval
Source location
Quote 56708, Carbon Ave canal crossing
Lead-time band
4 to under 12 weeks
Range width
1 weeks
Duration format
Bounded range

Technical context · Precast concrete drainage structures · NPCA technical overview of box culverts

“Precast concrete box and 3-sided culverts are incredibly versatile”