Rooftop HVAC units above 50 tons
“RTUs (>50 ton) 13-22 weeks”
Reading details
- Reading period
- 2026-Q1
- Publisher
- Gilbane Building Company
- Reading type
- Market report
- Lead-time basis
- From order or fabrication release
- Source location
- Q1 2026 lead-time table
- Lead-time band
- 12 to under 26 weeks
- Range width
- 9 weeks
- Duration format
- Bounded range
Technical context · Air distribution and rooftop HVAC · Trane VAV system guide
“A typical VAV system consists of a rooftop unit, water-cooled self-contained unit, or an air handling unit”