Medium-voltage cable

30–45 weeks

“However, medium voltage cable lead times are still in the 30-45 week range.”
Skanska USA Building · Spring 2023, Electrical · Checked 28 Nov 2026

Reading details

Reading period
2023-Spring
Publisher
Skanska USA Building
Reading type
Market report
Lead-time basis
Market lead time
Source location
Spring 2023, Electrical
Lead-time band
26 to under 52 weeks
Range width
15 weeks
Duration format
Bounded range

Technical context · Medium-voltage cable · Okonite cable class catalog

“Medium Voltage Cables 2.4kV and above”