Concord, North Carolina, recorded 8–10 weeks for a 24,000-foot order of 1/0 15 kV primary cable in February 2026. Read the evidence.
Monthly supplier index
First release pending. Suppliers can submit a shipment estimate for the fixed specification.
Published readings by period
Use the reading type and clock to match evidence to your purchase.
-
2026-02
- WESCO 1/0 15 kV primary cable, 24,000 ft · Public bid · 8–10 weeks
-
2026-01
- Border States / Prysmian — 15 kV 1/0 solid aluminum cable in duct · Public bid · 30–32 weeks
- Border States / Prysmian — 15 kV 1/0 solid jacketed aluminum cable · Public bid · 24–26 weeks
- Border States / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable · Public bid · 24–26 weeks
- Border States / Prysmian — 15 kV 750 stranded jacketed aluminum cable · Public bid · 24–26 weeks
- IRBY / Okonite — 15 kV 1/0 solid aluminum cable in duct · Public bid · 32–34 weeks
- IRBY / Okonite — 15 kV 1/0 solid jacketed aluminum cable · Public bid · 30–32 weeks
- IRBY / Okonite — 15 kV 4/0 stranded jacketed aluminum cable · Public bid · 34–36 weeks
- IRBY / Okonite — 15 kV 750 stranded jacketed aluminum cable · Public bid · 26–28 weeks
- RESCO / Prysmian — 15 kV 1/0 solid aluminum cable in duct · Public bid · 31–33 weeks
- RESCO / Prysmian — 15 kV 1/0 solid jacketed aluminum cable · Public bid · 25–27 weeks
- RESCO / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable · Public bid · 25–27 weeks
- RESCO / Prysmian — 15 kV 750 stranded jacketed aluminum cable · Public bid · 25–27 weeks
- WESCO / CME — 15 kV 1/0 solid aluminum cable in duct · Public bid · 32–34 weeks
- WESCO / CME — 15 kV 1/0 solid jacketed aluminum cable · Public bid · 30–32 weeks
- WESCO / CME — 15 kV 4/0 stranded jacketed aluminum cable · Public bid · 34–36 weeks
- WESCO / CME — 15 kV 750 stranded jacketed aluminum cable · Public bid · 26–28 weeks
- WESCO / LS Cable — 15 kV 1/0 solid aluminum cable in duct · Public bid · 26 weeks
- WESCO / LS Cable — 15 kV 1/0 solid jacketed aluminum cable · Public bid · 22 weeks
- WESCO / LS Cable — 15 kV 4/0 stranded jacketed aluminum cable · Public bid · 22 weeks
- WESCO / LS Cable — 15 kV 750 stranded jacketed aluminum cable · Public bid · 22 weeks
-
2025-08
- Power Line / Okonite 500 MCM Cu URD MV cable, 15 kV · Public bid · 8–10 weeks
- RESCO / Kerite 500 MCM Cu URD MV cable, 15 kV · Public bid · 10 weeks
-
2023-Spring
- Medium-voltage cable · Market report · 30–45 weeks
-
2022-Summer
- Nonstock 5–15 kV cable · Market report · 14–20 weeks
-
2022-Spring
- Volume purchase of 5 kV cable · Market report · 20–28 weeks
MV cable buying questions
How do I compare the Rochester bids fairly?
Match the bid item and stock number first. The source location identifies the line, requested footage and bidder, including the two WESCO manufacturer options.
What should a medium-voltage cable RFQ include?
Specify voltage class, conductor material and size, insulation, shield, jacket, total footage, reel lengths and requested ship date.
When does the quote clock start?
Use the timing basis on the bid. When the bid lists only a lead-time column, record the intended start milestone in the purchase order.
Request quotes
Send the part specification, quantity, delivery ZIP code and deadline to the procurement desk.
Request received by the procurement desk.
If the form fails, email desk@industrialleadtimes.com with your brief.