Water-cooled chillers below 1,000 tons
“Chillers (Water Cooled, <1000 tons) 18-30 weeks”
Reading details
- Reading period
- 2026-Q1
- Publisher
- Gilbane Building Company
- Reading type
- Market report
- Lead-time basis
- From order or fabrication release
- Source location
- Q1 2026 lead-time table
- Lead-time band
- 12 to under 26 weeks
- Range width
- 12 weeks
- Duration format
- Bounded range
Technical context · Chilled-water plant equipment · Trane chiller technical guide
“Air-cooled chillers use fans to blow air over the condenser, while water-cooled chillers transfer heat to a water loop”