Medium- and low-voltage switchgear
“lead times for electrical gear increased over the past quarter, specifically for medium- and low-voltage switchgear, which now exceed 52 weeks.”
Reading details
- Reading period
- 2026-Fall
- Publisher
- Skanska USA Building
- Reading type
- Market report
- Lead-time basis
- Excludes submittals
- Source location
- Fall 2026, Electrical
- Lead-time band
- 52 weeks and up
- Duration format
- Lower bound only
Technical context · Electrical distribution switching and protection · Eaton distribution switchgear overview
“provides centralized control and protection of medium-voltage power equipment”