Medium- and low-voltage switchgear

52+ weeks

“lead times for electrical gear increased over the past quarter, specifically for medium- and low-voltage switchgear, which now exceed 52 weeks.”
Skanska USA Building · Fall 2026, Electrical · Checked 28 Nov 2026

Reading details

Reading period
2026-Fall
Publisher
Skanska USA Building
Reading type
Market report
Lead-time basis
Excludes submittals
Source location
Fall 2026, Electrical
Lead-time band
52 weeks and up
Duration format
Lower bound only

Technical context · Electrical distribution switching and protection · Eaton distribution switchgear overview

“provides centralized control and protection of medium-voltage power equipment”