Switchgear lead times

Gilbane’s Q1 2026 survey reported 49–82 weeks for medium-voltage switchgear after order or fabrication release. Read the evidence.

Published readings by period

Use the reading type and clock to match evidence to your purchase.

  1. 2026-Fall

  2. 2026-Q1

  3. 2022-Summer

Switchgear buying questions

What date starts the Gilbane estimate?

The estimate begins when the order or fabrication is released. Put engineering and submittal approval on separate lines in the schedule.

How are open-ended readings shown?

A plus sign marks a lower bound. The upper end stays blank in the data export.

Which specifications help line up switchgear quotes?

Match voltage, ampacity, short-circuit rating, lineup size, relay package, enclosure and acceptance test scope.